October 2026

MDL WHLS: pushing the vessel envelope

The Wheeled Horizontal Lay System is creating new routes into deepwater installation and recovery

The King’s Award for Enterprise in Innovation recognised MDL’s Wheeled Horizontal Lay System (WHLS) as an efficient enabler for challenging cable lay and flexible decommissioning. Its real value, however, is not simply in the equipment itself - it lies in the options that become available when high-capacity handling can be engineered onto a vessel already accessible to the project.

For operators, vessel owners and offshore contractors working in deep water, the traditional route has often been clear: secure specialist construction tonnage or reconsider the scope. The first option can be the right answer, particularly for long-duration or highly specialised campaigns when extended vessel charter makes commercial sense. This perpetuates the challenge for smaller, isolated or time-sensitive scopes, which may struggle to align a dedicated construction vessel with their operational window and project budget.

The consequence is often a delayed campaign or a costly vessel solution sourced from afar… or a new approach to scope execution.

MDL front-end engineering track record has already demonstrated that when product data, vessel capability and operational constraints are understood early enough, a locally available support vessel may be configured to carry out demanding installation or recovery work with confidence.

This is the thinking behind the WHLS. It was developed to remove a practical limitation in high-load flexible recovery, but it has since demonstrated its relevance across two very different types of subsea work: SURF decommissioning and multi-line cable installation.

Start with the operation, not the vessel label

An Offshore Support Vessel does not become a deepwater lay or recovery asset simply by adding equipment to its back deck. The question is whether a specific vessel can be configured around a particular product and the operating conditions. That means understanding where the product will be handled, how it will transition from deck to sea, and where additional friction or bending forces could limit the operation.

Deepwater SURF recovery is governed by the usable pull available at the point of handling. A high-capacity tensioner may have the required nominal line pull, yet still be unable to recover the product if a significant proportion of that pull is consumed before the flexible reaches the vessel deck.

This is the capstan effect. In a conventional horizontal lay arrangement, the product passes over a fixed chute during recovery. Friction between the flexible and the chute adds to the tension required at the tensioner. The deeper the water and the higher the recovery load, the more material that additional resistance becomes. A 100Te recovery load can require a tensioner capable of substantially more than 100Te once the friction created by a fixed overboarding route is included.

The WHLS addresses that limitation by replacing the static chute interface with an integrated wheel. The product travels over a rolling surface, significantly reducing friction and preserving a far greater proportion of the tensioner’s available pull. This enables MDL’s high-capacity single-unit tensioners to work closer to their full capability, without adding a second unit simply to overcome resistance at the chute.

Proven from first application

The original WHLS-100 was developed to tackle this exact challenge. It was deployed by Brazilian contractor Ocyan for deepwater subsea decommissioning work in the Campos and Sergipe-Alagoas Basins. The contractor needed a portable recovery system able to handle the loads associated with retrieving large volumes of flexible infrastructure from mature fields. A conventional Horizontal Lay System formed the starting point – and this is where the engineering work identified that friction over a chute would significantly reduce the available recovery capacity – the aforementioned capstan effect.

Fast forward from the delivery of the system and the mobilisation of a spread on a Construction Support Vessel (CSV) in Peterhead, Scotland, to Ocyan’s deployment of this new decom asset offshore Brazil. They subsequently recovered 275km of subsea pipes and cables from depths of 800 to 1,700m, supporting what the company describes as the country’s first deepwater offshore subsea decommissioning project.

As far as trials go, this was a serious one – proving the WHLS through a substantial operational campaign, handling the realities of flexible recovery at depth: varying product sizes, long-duration operations, offshore logistics and the requirement to retain control of ageing infrastructure throughout retrieval.

More importantly, it established that a portable, high-capacity recovery route could be built around a project requirement as a safe alternative in the absence of a dedicated PLSV.

One design, multi-sector application

The system’s next major application demonstrated how the same low-friction handling principle can support a very different offshore challenge.

At the Mero field in the Santos Basin, Maersk Supply Service needed to install a Permanent Reservoir Monitoring assembly comprising a dynamic umbilical riser, Data Unit Transfer Assembly and five connected pigtails. The complexity was not simply the water depth or line pull: the product had to be deployed as one connected arrangement, with control of the bundle required throughout initiation, transfer and overboarding.

MDL completed a FEED study to define the installation methodology, comparing tensioner configurations, deck layouts, squeeze settings and routing paths. The selected solution used bespoke W-pads to grip the umbilical and pigtails as a stable package, alongside the WHLS to guide the assembly through the vessel moonpool.

The project clearly illustrated that the WHLS is not defined solely by recovery. Its wheel mechanism also supports controlled, low-friction deployment where product geometry and handling integrity shape the installation method.

A subsequent Campos Basin decommissioning campaign returned the focus to high-load recovery. The field operator had an Offshore Support Vessel already under charter and wanted to establish whether it could be repurposed for a SURF retrieval scope. MDL’s FEED study assessed the vessel, defined the recovery methodology and developed the back-deck configuration before the equipment package was selected.

Here, the wheeled overboarding arrangement enabled a single 110Te tensioner to handle recovery loads of up to 105Te. The campaign was completed 19 days ahead of the client’s forecast, using the vessel already committed to the field rather than requiring a specialist decommissioning asset.

These three projects answer different operational challenges. Ocyan demonstrated the system’s ability to support large-scale deepwater SURF recovery from its first offshore application. Mero applied the design to a complex installation scope, where product control was as important as pull capacity. The Campos Basin campaign showed how FEED, equipment and project delivery can convert an existing vessel into a technically defined recovery route.

Engineering makes the alternative credible

A vessel-of-opportunity approach is not an off-the-shelf substitute for a PLSV.

While the principle behind the Wheeled HLS seems straightforward, its application requires careful engineering. Product behaviour, bend radius, route, load profile and vessel arrangement still determine the final method.

All are engineering questions; addressed early, they establish whether an existing vessel can support the scope and what combination of equipment, personnel and procedures is required. Left until mobilisation, they can become the reason a technically achievable campaign becomes more expensive, delayed or dependent on specialist tonnage.

For familiar, lower-complexity scopes, an experienced project team can often select and mobilise a proven MDL spread quickly. High-load deepwater recovery and complex installations call for a more detailed engineering phase. In this case, feasibility studies create value by evaluating the available options before the project commits to a vessel route, equipment package or schedule. It also provides the practical basis for mobilisation planning, local contractor coordination and offshore execution.

That is where MDL Integrated Project Services brings particular value. The WHLS is one part of the answer; but in each of these projects, it was supported by engineering analysis, equipment integration, mobilisation planning, local coordination and experienced offshore personnel. Bringing those elements together gives the client one connected path from feasibility to offshore delivery, rather than a collection of separate interfaces to manage.

A relevant capability for the Americas

MDL now has two WHLS units within its Flexlay Solutions fleet, creating capacity to support deepwater installation and recovery opportunities across the Americas.

Brazil combines deepwater field activity with a substantial requirement to recover ageing subsea infrastructure. In the US Gulf, operators and contractors face many of the same commercial pressures: demanding water depths, complex products, tight vessel schedules and a need to make sound choices around specialist construction tonnage.

The system gives project teams a practical option when conventional overboarding arrangements limit usable pull. It gives vessel owners a route to assess additional flexlay capability. It gives contractors an opportunity to look beyond the availability of dedicated construction tonnage and establish whether an existing vessel can support the operation.

Where a deepwater scope is being shaped around vessel availability, MDL can assess the options early and define the route from feasibility through to offshore delivery. Get in touch.